Which supplier delivers first when one quotes three weeks and the other four?

Three weeks from material arrival and four weeks from PO receipt use different clocks. Compare the start event, finishing, inspection and arrival date.

Kairen2 min read

A slipping assembly schedule puts pressure on purchasing to pick the shop quoting three weeks. But what if those three weeks start on material arrival, while the other shop’s four start when it receives the order today? The assembly team still needs a date it can plan around.

Ask both suppliers for the same milestone

In Kairen Covenant’s fictional bracket example, the buyer needs 300 pieces to Rev C. Supplier A quoted KRW 18,000 per part and three weeks for 1,000 pieces to Rev B. Supplier B quoted KRW 21,000 per part and four weeks for 300 pieces to Rev C.

Get a Rev C, 300-piece requote from A, then ask both shops, “If we order today, when will finished, inspected parts arrive at our facility?” Have each supplier name its start event and say whether the end date means dispatch or receipt. Confirm time for finishing and inspection separately from the fees for those steps.

Check the lead-time assumptions in the Kairen Covenant demo

How credible is the promised date?

Given each shop's current machine load, backlog, and raw-material availability, how likely is either supplier to actually hit its promised 3-week or 4-week delivery date?

Ask each shop when its material will be available and which production slot it can commit to. That gives assembly a date grounded in current conditions.

FAR 11.403(a) distinguishes calendar dates from periods tied to a contract date, notice or order receipt. Material arrival and drawing approval are examples for this purchasing scenario.1

Notes

  1. Acquisition.gov · FAR 11.403 — Supplies or services ↩

References

  1. FAR 11.403 — Supplies or services. Acquisition.gov.

Cite this article

Kairen. “Which supplier delivers first when one quotes three weeks and the other four?.” Kairen Insights, November 21, 2026. https://kairenhq.com/insights/when-does-supplier-lead-time-start

About Kairen

Kairen builds sourcing software for product teams and suppliers to agree on part specs, prices, and delivery dates as designs take shape.

Explore Kairen Covenant